Office Fitout Case Study — 3,500 sqft in Sector 132, Noida
Aarna 2025 project: 3,500 sqft commercial office fitout for a fintech startup in Sector 132, Noida. Open-plan + 3 cabins + 2 meeting rooms + pantry. Fire NOC handled in-house. 6-week delivery, Rs 42 lakh turnkey.
The owner brief
Fintech startup (Series A, 35 employees) signed a 3,500 sqft commercial space in a Sector 132 tower. Their brief: a modern, calm, design-forward office that helped recruiting + matched their brand colours (navy + white + accent green).
They had 6 weeks from lease handover to opening. Hard constraint: fire NOC must be in place before move-in (their compliance team required it). They'd interviewed 4 fitout firms; Aarna won by guaranteeing fire NOC in-house within timeline.
Design lock in 8 days. Build started week 2. Office opened on week 7 exactly on schedule.
What the brief looked like
Fire NOC within 4 weeks: UP Fire NOC typically takes 3-4 weeks. We submitted on day 1, inspection in week 3, NOC issued week 4 — in time for move-in.
IT cabling backbone: 40 workstations + 5 enclosed rooms need structured cabling. We planned floor box + raceway layout in week 1; cabling laid week 4 before furniture install.
HVAC capacity: Building HVAC was sized for old tenant (60% of new capacity needed). We added 4 VRF indoor units for cabin + meeting room load.
Brand colour integration: Frosted-glass cabin partitions with company logo etched. Coordinated with their brand team for exact Pantone colour match.
Itemised cost breakdown
| Phase / item | Cost | Notes |
|---|---|---|
| Civil + drywall partitions | Rs 4.8 L | Cabin + meeting room walls |
| HVAC (4 additional VRF IDUs) | Rs 5.2 L | Daikin + commissioning |
| Workstations (40 nos) | Rs 9.8 L | Featherlite Premium modular |
| Cabin furniture + meeting tables | Rs 4.2 L | 3 cabins + 2 conference tables |
| Glass partitions (cabins + meeting) | Rs 3.6 L | 10mm tempered + frosted branding |
| Mineral fibre ceiling + lighting | Rs 3.8 L | Grid + 600x600 LED panels |
| Flooring (vitrified + LVT in meeting) | Rs 3.2 L | Mix for zoning |
| Pantry + breakout | Rs 1.8 L | Modular pantry + breakout seating |
| IT cabling + network + UPS | Rs 2.4 L | Structured cabling Cat 6A + UPS room |
| Fire safety + NOC handling | Rs 1.2 L | Sprinklers + extinguishers + NOC fees |
| Paint + brand colour accent walls | Rs 1.4 L | Navy + green accent |
| PM + supervision + contingency | Rs 0.6 L | 6-week dedicated PM |
| TOTAL turnkey | Rs 42.0 L | Within Rs 1,200/sqft standard tier |
Build timeline — week by week
Week 1: Brief + design lock + fire NOC submission
8 days to lock, fire NOC submitted day 1
Week 2: Civil + drywall partitions + HVAC start
Cabin + meeting room walls built
Week 3: HVAC commissioning + fire inspection
Daikin VRF commissioned, fire dept site visit
Week 4: Cabling + ceiling + lighting
Cat 6A cabling + LED panels + UPS
Week 5: Flooring + paint + glass partitions
Vitrified + LVT + frosted glass install
Week 6: Workstations + furniture + final fittings
Featherlite Premium + cabin desks + chairs
Week 7: Pantry + breakout + IT testing + handover
Modular pantry + Cat 6A speed test passed
Move-in: Week 7 + fire NOC ready
Office operational on day 1 of move-in
Materials & brands used
Project gallery
We had a hard 6-week deadline before opening. Aarna delivered with the fire NOC in place. The frosted-glass branding was Pantone-accurate. Three quarters in, our team productivity numbers are up; the office quality is part of why.